Dresden Neustadt: Temporary district heating pipe saves you from the cold!

Transparenz: Redaktionell erstellt und geprüft.
Veröffentlicht am

In Dresden Neustadt, a temporary district heating pipe will be laid across the Augustus Bridge from Monday to ensure winter demand.

Dresden Neustadt: Temporary district heating pipe saves you from the cold!

In Dresden Neustadt, a temporary district heating pipeline will be installed over the Augustus Bridge to ensure heat supply in the coming winter. This measure became necessary after the connection was damaged by the collapse of the Carola Bridge.

The specialists will begin the welding work on Monday. The individual pieces of pipe are connected and gradually laid over the footpath of the bridge to ensure that residents do not have to freeze during the cold months.

Important steps for district heating supply

The goal of the work is clearly defined: On October 22nd and 29th, 2024, the connecting pieces to the temporary lines that will be integrated into the district heating network are to be installed. The existing pipes are cut open and T-pieces are installed, which are also fixed by welding.

In order to protect the historic structure and prevent damage, the gravel underneath the bridge was removed. In its place, a special fleece is laid out onto which the concrete is then poured. These preparatory measures are essential to ensure the stability and integrity of the bridge during construction. In addition, the paving slabs will be stored during the work so that the structure of the building is not affected.

The city administration hopes that these measures will ensure a reliable heat supply for the new town and thus guarantee the comfort of residents even in the cold season. The entire project is being carried out with care to ensure both the functionality of the district heating pipeline and the preservation of the historic building. For more details on this topic, see the report on www.radiodresden.de.