Full closure at Theodor-Heuss-Ring: Derirandings from October 2024!
Full closure at Theodor-Heuss-Ring: Derirandings from October 2024!
In Leverkusen, there is a comprehensive construction measure on the Theodor-Heuss-Ring, which is carried out on several sections from October 2024 to January 2025. This measure is implemented as a "hiking construction site", which means that the work is done in different phases in order to keep the traffic load as low as possible and at the same time make the necessary improvements.
The first construction phase begins on October 7, 2024 and is expected to be completed by November 3, 2024. During this time, the Theodor Heuss ring between house numbers 76 and 78 is completely blocked. However, it is ensured that the residents of house numbers 78 to 91 continue to have access to their homes. The blocking is necessary to carry out comprehensive work that is essential for the long -term improvement of the infrastructure.
construction phase planning and traffic redirection
Following the first section, the second construction phase follows, which is planned from November 4 to December 15, 2024. The Theodor-Heuss-Ring between house number 78 and up to number 108 is completely blocked. The temporary restrictions are necessary to carry out great technical work that will ensure a secure road.
The third and last construction phase is planned for the period from December 16, 2024 to January 31, 2025. Here, too, a full closure of the Theodor Heuss ring will be required, from the height of the number 108 to the confluence with the Käthe-Kollwitz-Straße. These final work is crucial for the complete modernization and the final grinding of the street infrastructure.
To minimize the disabilities, a detour is set up via Steinbücheler Straße. Pedestrians are safely guided past the construction site during the entire construction period, so that the safety of all road users is guaranteed. These precautions are the result of intensive votes between the construction site coordination, the fire brigade Leverkusen, Wupsi GmbH and the Cologne police to ensure smooth running during the construction work.
The technical companies of the city of Leverkusen ask the residents and road users for understanding possible impairments during the construction period. These measures contribute to improving traffic management and the general quality of life in the city, which is why temporary patience is required.
For further information on the construction work and the associated changes in traffic, a detailed look at the current reporting can be taken to keep up to date with all news and developments. A comprehensive overview is to be found here .