Construction work on L54 in Vetschau: Asphalt start is shifting to November 2024!
Construction work on L54 in Vetschau: Asphalt start is shifting to November 2024!
shock in Vetschau: The highly expected asphalt work on the L54 state road were suddenly moved! Instead of the end of October 2024, asphalt installation will not take place until the end of November 2024, and for no less than two decisive reasons. Unexpected additional work on the wastewater pressure line makes an adjustment of the schedule necessary, and there are also the current delivery bottlenecks for components that also delay the whole thing!
The official bodies reported that despite these setbacks, the planned completion of the construction work remains in August 2026. "The diversion for road users remains and we advise you to continue to use the designated routes," warns the State Roads. However, those affected are asked for patience and understanding during the construction work, because there can also be smaller restrictions in residents and commercial traffic.
reason for the delays
The delay is due to the additional renewal of the wastewater pressure line and the associated replacement of a dash shaft. The Situation is a real test of patience for residents and traders. There is no reason to panic, but the organization has its challenges: While the work continues, security and accessibility remains the top priority for all road users.
Details | |
---|---|
Ort | Vetschau, Deutschland |
Kommentare (0)