Kuhmoosbachbrücke: Finally free trip from December 6th in sight!

Kuhmoosbachbrücke: Finally free trip from December 6th in sight!

Villingen-Schwenningen, Deutschland - The renovation work on the Kuhmoosbach Bridge on the L181 between Pfaffenweiler and Villingen is progressing! The Freiburg regional council has announced that the street is expected to be opened for traffic again on December 6th. After weeks of delays caused by heavy rain and construction defects, the construction site will be completed on December 5. Drivers who have often had long detours in recent months can breathe a sigh of relief!

progress in construction work

On Friday, November 8th, the last concreting work on the bridge was carried out. Project manager Wolfgang Thedy reported that large equipment was opened for the construction work in order to make the ground viable. The excavated excavation excavated to the side is mixed with lime and compressed in layers. As soon as the concrete of the new reinforced concrete bridge has hardened, the floor above the bridge is poured to about 1.50 meters. The next step? The asphalt installation!

If everything goes according to plan, drivers can use the L181 unhindered from December 6th. Those responsible are optimistic, even if there are small reservations. The construction work is now well on schedule after the original schedule has been updated in September. The anticipation for the reopening of the street increases, and the hope of returning to normality is tangible!

Details
OrtVillingen-Schwenningen, Deutschland

Kommentare (0)